2012 Storm Water System Improvement To Vacant Lot at 806 Brenner

The city purchased the unbuildable lot at 806 Brenner late in 2011 and extended a larger storm sewer inlet to the middle of the lot in September of  2012.  The new storm sewer is connected directly to the large storm sewer pipe that runs directly to Lake Owasso (most of the curbside catch basins are connected via smaller pipes to Charlie Pond north of the Millwood cul-de-sac).  This completes the work described in Summary of storm sewer work to be performed in October 2007.